PROJECT : PWA/GTC/022/2018 ROADS AND INFRASTRUCTURE IN SOUTH OF AL MESHAF - PACKAGE 01 IA/2018/C/037/G
CLIENT: PUBLIC WORKS AUTHORITY (ASHGHAL)
DATE OF COMMENCEMENT: MARCH 2019
SCHEDULE OF COMPLETION: SEPTEMBER 2022
LOCATION: Al MESHAF - DOHA
ROLE : JOINT VENTURE PARTNER CONTRACTOR (SACYR-MEDGULF JV)-MEDGULF ( 51% PARTNER )
Project Description:
The project includes infrastructure development around 9726 residential plots, 1600 commercial plots, 4 schools, 3 reserved government plots,21 mosques, 13 parks and 226 open space / green areas.
The proposed project will result in the construction of a single, dual carriageway and expressway road network within proposed corridors of 64m, 50m, 40m, 24m, 20m, 16m, 12m and 5-8m width in accordance with the MoTC standards
Scope of Works:
- Road Network with fully paved carriageways, including signalized junctions (traffic Signals) and Roundabouts at grade; with provision for pedestrians and cyclist
- On street parking layout and configuration
- Kerblines and footways adjacent to roads
- Road signs ( including signage gantries), lighting and road markings as required
- Complete Surface water and Groundwater drainage system to function during and after the construction period
- Section of Al Wakra Tunnel for Surface water and Groundwater
- Advance direction signs and street signs.
- Pump Station complete with infrastructure including header tank, mechanical and electrical equipment, control and instrumentation, treatment facilities, ancillary buildings, access roads, surface water twin rising mains, groundwater rising main, valve chambers, drainage, etc.
- Groundwater discharge and monitoring boreholes
- Complete Foul Sewer Network, including House Connection up to Stage 1 only
- Soft and hard landscaping
- Treated Sewage Effluent (TSE), complete with SCADA provision and irrigation main lines
- Complete Potable Water Network including protection and diversion of existing mains;
- Full Electrical Network Designs, including Road Lighting – Local Roads, Electricity Networks – MV & LV, Distribution Substations – 11/0.415kV, Distribution Substations – 11/0.415kV
- Mobilisation, Site offices, Site plant, fencing, walls and other accommodation works