SL. No | PROJECT NAME | TYPE OF WORK | START DATE | END DATE |
01 |
RAS LAFFAN OLEFINS COMPANY LTD (RLOC) |
RL-TC-T-02-17 EPIC OF NEW SANITARY WATER TREATMENT PLANT AT RLOC The objective of this “Brown field project” EPIC scope of work is demolition and disposal of existing sanitary treatment plant and installation of “New Sanitary Water Treatment Package” with associated process engineering, piping, civil/ structural, |
09th NOVEMBER 2017 | 09th OCTOBER 2018 |
02 | QATAR PETROLEUM |
GC161058A0 EPIC OF METERING SYSTEM AT MESAIEED (PART A) Design, procure, Install and commission Facility new Coriolis mass flow meter order to mitigate the discrepancies in the quantity of supply of butane through the current butane flow metering system installed in NGL and the quantity of butane received through the meter at QAFAC.. Scope: CIVIL/STRUCTURAL 1. Existing Metering Skid Foundation will be utilized. 2. A second emergency exit in the form of a structural steel crossover shall be provided over the firewater pipeline trench adjacent to the flow meter skid. PIPING 1. New Metering Skid with Duplex Strainer 2. Piping Modifications ELECTRICAL 1. Electrical Power Supply from UPS DB (at LER 3400) to new Metering Skid. INSTRUMENTATION 1. New Flow computer panel shall be installed for monitoring the flow of butane to QAFAC at LER-3400 (Extension).The flow computer shall be interfaced with existing GE Fanuc CIMPLICITY SCADA in NGL 1 & 2 CCB for monitoring and control. 2. Modification of Existing PLC and F&G system. LOSS PREVENTION HAZID Study |
04th JANUARY 2017 | 06th JULY 2018 |
03 | QATAR PETROLEUM |
GC16105500 EPIC FOR MITIGATION OF PIPING VIBRATION AND NOISE AT RG PLANT DUKHAN
PRE-SHUTDOWN ACTIVITIES Civil/Structural Piping SHUTDOWN ACTIVITIES Piping Area –D
Instrumentation Re-installation of SDV and Cable re-termination with all Pneumatic tubing works |
18th JULY 2016 | 17th APRIL 2017 |
04 | RAS GAS | D6803 FAXP BEACHPULL ASSISTANCE AND ONSHORE PIPELINE WORKS
FAP Scope Covers Onshore Storage, Pumping & Loading facilities that will pump MEG Via HP Pipeline to 8 RG & 3 QG Offshore WHPs allowing MEG Injection into the offshore wet gas pipelines to prevent formation of Hydrates. Scope: 1. Setting of the TSF Facilities for MHEL & MG till completion of Project |
1st MAY 2016 | 31th MAY 2017 |
05 | RAS GAS | D6938 – BARZAN PIPELINE REPAIR PROJECT – ONSHORE WORKS | 26th JANUARY 2016 | 10th OCTOBER 2016 |
06 |
RASGAS/ CHIYODA ALMANA |
[RGCP-475] PROCUREMENT, INSTALLATION, CONSTRUCTION AND PRE-COMMISSIONING OF ALL FACILITIES RELATED TO THE COMPLETION OF LNG ROAD TANKER LOADING FACILITY PROJECT (RFS 128-003) a) Objective of this project is to design, procure, construct and install suitable facilities and equipment that will facilitate the loading of LNG onto RLC procured road tankers. b) New LNG loading supply facility to be constructed adjacent to RG Tank Farm area |
23th JUNE 2015 | 30th JULY 2016 |
07 |
QATAR GAS |
STC-C-VEN-3066-17 EPC FOR INSTALLING SCALE BASKETS IN LAFFAN REFINERY | 08th OCTOBER 2017 | 08th OCTOBER 2018 |
08 |
QATAR GAS |
STC-C-VEN-2920-16 EPC SERVICES FOR PRV OUTLET PIPING MODIFICATION | 10th JULY 2017 | 10th JULY 2018 |
09 | QATAR GAS | LTC-C-VEN-2730-16 EPC SERVICES FOR REPLACEMENT OF SPRINKLER SYSTEM CHECK VALVES AT QG HQ BUILDING, WAREHOUSE AND CANTEEN IN RL | 22nd MARCH 2017 | 20th SEPTEMBER 2018 |
10 | QATAR GAS | STC/C/VEN/2840/16 EPC SERVICES FOR ADDITIONAL CAR PARKING IN LR | 26th MARCH 2017 | 25th NOVEMBER 2017 |
11 | QATAR GAS | STC-C-VEN-2733-16 EPC Services For Upgrade of Motor Purge System For Compressor K-1501and K-1601 at LR | 01st MARCH 2017 | 01st OCTOBER 2018 |
12 | QATAR GAS | LTC-C-VEN-2794-16 EPC FOR REINSTALLATION OF SODIUM HYPOCHLORITE INJECTION PACKAGE AT LAFFAN REFINERY | 12th FEBRUARY 2017 | 12th JULY 2018 |
13 | QATAR GAS | STC-C-VEN-2742-16 EPC FOR INSTALLATION OF NEW CABLE TRAY AT CLLNG BERTH-1 | 08th FEBRUARY 2017 | 08th JANUARY 2018 |
14 | QATAR GAS | STC-C-VEN-2234-15 PROVISION OF RE-RANGE NITROGEN LOOPS HYDROCARBON ANALYSERS IN QG2, AND QG3&4 | 08th FEBRUARY 2017 | 08th OCTOBER 2018 |
15 | QATAR GAS | LTC/C/VEN/2727/16 EPC SERVICES FOR INSTALLATION OF NEW BYPASS LINE | 09th JANUARY 2017 | 08th MARCH 2018 |
16 | QATAR GAS | LTC/C/VEN/2376/15 PROVISION OF ICE FALL PROTECTION NETS ON EACH LOADING ARM OF QATAR GAS LNG BERTH 1, 4, 5 & 6 | 01st AUGUST 2016 | 31st MARCH 2018 |
17 | QATAR GAS | REPLACEMENT OF CURRENT TRANSFORMER OF GTG AUXILARY TRANSFORMER IN QG 2 | 03rd JANUARY 2016 | 30th MARCH 2017 |
18 | QATAR GAS |
SCOPE: Replace existing high expansion foam skids 02-XZ8301-PT2-05, 02-XZ8306-PT2-09 and 03-XZ8301-PT3-05 with new high expansion foam skids with fixed flow inductor and their corresponding foam generators |
05th NOVEMBER 2015 | 04th NOVEMBER 2016 |
19 | QATAR GAS |
STC/C/VEN/1698/14 - EPC SERVICES FOR UPGRADING OF H2SO4 SYSTEM IN QG2 & RE-LOCATION OF RCM PANEL IN FIRE WATER LINE NETWORK IN REFINERY EPC SERVICES FOR following 2 (Two) Projects,
|
26th JULY 2015 | 30th NOVEMBER 2016 |
20 | QATAR GAS | EPC SERVICES FOR PROVISION OF BUND WALL FOR POLISHING PACKAGE SPILL CONTAINMENT AND PIPE RACK BRIDGE PROTECTION LR AREA | 03rd AUGUST 2015 | 31th MAY 2016 |
21 | QATAR GAS | LTC/C/VEN/1699-B/14-REPLACEMENT OF CONTROL VALVE 81-PV-1333 IN LAFFAN REFINERY | 30th APRIL 2015 | 30th APRIL 2016 |
22 | QATAR GAS |
LTC/C/VEN/1669/14 - EPC SERVICE FOR REPLACEMENT OF HYDRAULIC TUBING OF KANON LOADING ARM ON JETTY 3 Scope: 1. Engineering, procurement, construction for replacement of hydraulic tubing of Kanon Loading Arm which are installed in Jetty 3 in Ras Laffan Terminal Operation (RLTO) area. 2. Replacement of existing hydraulic tubing with higher metallurgy i.e Nickel Alloy 625, Monel k 400 or k 500. |
12th APRIL 2015 | 30th OCTOBER 2016 |
23 | QATAR GAS | LTC/C/VEN/1553B/14- QG1 TEMPORARY POWER BRIDGING EPC
The objective of this project is to carryout the Engineering, Procurement and construction works required for the installation, tie in and commissioning of COMPANY Free Issue one TM2500+ Gas Turbine Generator(GTG) and associated balance of Plant (BOP) equipment. This is to be installed at the Qatargas 1. Medgulf role shall be installation of GT and necessary electrical power tie in for the gas turbine. |
2 MARCH 2015 | 30th MARCH 2016 |
24 | AIR LIQUIDE, / GASAL | ELECTRICAL & INSTRUMENATTION WORKS FOR GASAL RL W8-1, 2450 TPD AIR SEPARATION PROJECT
|
23rd APRIL 2015 | 28th FEBRUARY 2016 |
25 | AIR LIQUIDE, / GASAL |
STRUCTURAL STEEL WORK, MECHANICAL, PIPING AND PRE-COMMISSIONING WORK FOR GASAL RL W8-1, 2450 TPD AIR SEPARATION PROJECT
|
14th NOVEMBER 2014 | 30th SEPTEMBER 2015 |
26 | ORYX /TEHNIP MIDDLE EAST | CONSTRUCTION WORKS FOR ORYX DOT -023 DOT- 025 & DOT – 027-Brownfiled |
02nd SEPTMEBER 2014 | 30TH APRIL 2016 |
27 | GASAL | 50-3514-00 - GASAL RLW8-1- CIVIL WORKS
Scope:
|
1ST JULY 2014 | |
28 | QATAR PETROLEUM | TENDER NO. GT13107800 - EPIC FOR GAS SUPPLY TO RAF POWER STATIONS
Installation of two 36 inch pipelines with all required facilities to connect existing Station T21 to Station W2 which includes; Design & Detailed Engineering and Supply and Construction of Civil and Mechanical, Electrical, Instrumentation & Pipeline works. |
10th MARCH 2014 | 16th JANUARY 2016 |
29 | RASGAS | RASGAS ONSHORE FLOW ASSURANCE PROJECT
Scope:
|
26th FEBRUARY 2014 | 30 SEPTEMBER 2016 |
30 | ORYX GTL DOT | CONSTRUCTION WORKS FOR ORYX GTL DOT - 016 TECHNIP PROJECT No. 9643G-016
Fabrication, installation and commissioning of 7 sustainability projects |
24th FEBRUARY 2014 | 30th JANUARY 2015 |
31 | RLOC | RAS LAFFAN OLEFIN PROJECT LOW PROFILE FLARE REPAIR WORKS CONTRACT NO. 9913A-20-CS-01
|
02nd OCTOBER 2013 | 30th MARCH 2014 |
32 | RASGAS |
RGP-365 [RFS-094] QP CONDENSATE SUPPLY PROJECT a) Underground pipe installation of 6” condensate line, FW and WPT line. b) 16 Hot taps 1” to 6” size in Train 1, Utility and RLC area c) Painting of piping spool and Pipe support. d) Tie-in activities, Hydro testing of New and existing lines after modification. e) Hot insulation of pipe and valve f) Cable trench excavation and backfilling g) Installation of new cable tray h) Electrical & Instrumentation Works i) Installation of 6” ESD valve and field instruments. j) Installation of pump, metering and prover skid k) Lighting fixer installation for new platforms. l) Sub grade preparation, excavation of equipment foundation and underground piping m) Civil foundations, Paving, Valve Pit, Duct bank and Sewer underground piping n) HDD or tunneling below off plot pipe corridor o) Assistance for pre commissioning and commissioning p) C P installation for underground lines |
14th AUGUST 2013 | 30th OCTOBER 2016 |
33 | QATARGAS |
9343F-001] JBOG RECOVERY PROJECT FOR QATARGAS- Subcontract for Construction works a) Prefabrication and erection of above ground piping works (10,000 Dia Inch ) b) Electrical works in the units and substation c) Instrumentation works in the units and in technical rooms / control room including loop testing from control systems such as DCS/ESD/PLC. d) Civil and structural works include earthworks, road, site preparation, gravity pipe networks, concrete works and shelter construction. e) Insulation works. f) Painting works. g) Pre-commissioning and commissioning. |
27th MAY 2013 | 02nd NOVEMBER 2014 |
34 | QATARGAS |
RFP-485] RGX ACID GAS AND MERCAPTAN GAS DIVERSIONS TO RGX2 SRUS PROJECT- MAIN CONSTRUCTION WORKS-RAS LAFFAN Construction, Fabrication, Hot-tap contracting, Hookup, Installation, Hydrotest, Pre-Commissioning and Commissioning assistance, including, New acid gas line with ESDV (40”, CS, steam traced, PWHT) – approximately 355 m Tie in to existing, New mercaptan gas line with ESDV (10”, CS, steam traced, PWHT) – approximately 235 m, Electrical, Instrumentation and Telecom works, Cathodic Protection & Fibre Optic Cable works. |
13th MAY 2013 | DECEMBER 2013 |
35 |
CHIYODA ALMANA ENGINEERING |
RHX-SA-027-001, RASGAS HELIUM 2 HEXU AND UTILITIES PROJECT, RAS LAFFAN Crude Helium Rundown Lines 10" & 20" app. 4.20 Km, Foundations and Steel Structure works, A/G Piping including Painting, Insulation & Fireproofing works, HeXU Cold Box, Electric Heater & Pump installation, Electrical, Instrumentation and Telecom works, Cathodic Protection & Fiber Optic Cable works. |
23rd AUGUST 2011 | 19th MARCH 2013 |
36 |
CHIYODA ALMANA ENGINEERING |
QG CONTRACT NO. LTC/E&V/1342/10 C4, QG HELIUM (II) PROJECT, RAS LAFFAN. Crude Helium Rundown Lines 12" & 14" app. 11 Km, Sleeper installation, Foundations and Steel Structure works, U/G and A/G Piping including Painting, Insulation & Fireproofing works, HeXU Cold Box, Electric Heater & Metering Skid installation, Electrical, Instrumentation and Telecom works, Cathodic Protection & Fibre Optic Cable works. |
06th JUNE 2011 | 21st APRIL 2013 |
37 |
FLUOR MIDEAST LIMITED |
J3BG-FML-9-F223 - JETTY BOIL-OFF GAS RECOVERY PROJECT, General Services AND Construction Support, RLIC. a) Supply of general labor;
|
30th DECEMBER 2010 |
05 JUNE 2016 |
38 | AIR LIQUIDE ENGINEERING | PROJECT NO: 8A342800, RAS LAFFAN HELIUM 2 RECOVERY PROJECT, GENERAL CONSTRUCTION WORKS (ORDER NO: 51342804/001)
|
07th OCTOBER 2010 |
03 JULY 2013 |
39 | QATAR GAS OPERATING COMPANY LTD |
CONTRACT NO. B6TH-40-K005, MARINE CONSTRUCTION ON THE COMMON LEAN LNG LOADING FACILITIES BERTH-6 Medgulf is responsible for Construction and Installation, Precommissioning and Commissioning of the following works:- a) Aboveground Stainless Steel & Carbon steel pipelines :-
b) Installation of following equipment :- c) Civil works including:- |
01st APRIL 2008 | 07th APRIL 2011 |
40 | QATARGAS 3&4 |
QG3&4/OFFS/C&I ONSHORE PIPELINE/013/2006 |
20th DECEMBER 2006 | 05th JULY 2011 |
41 | QATEX LIMITED | CONTRACT NO. 22005 / TC 01, CONSTRUCTION OF PIPELINE FROM MESAIEED TO AL-UDEID AIR BASE TERMINAL
|
26th MARCH 2008 | 06th JUNE 2011 |
42 | SHELL GTL | 5761-SC-10, ONSHORE WORKS FOR QATAR SHELL GTL LTD. – PEARL GTL PROJECT
|
17th DECEMBER 2007 | 31st MARCH 2010 |
43 | DOLPHIN ENERGY LTD. |
DC-PJ-5203, CONDENSATE AND LPG LOADING FACILITIES a) Fabrication, Installation, Painting, Insulation, Testing & Commissioning of:
|
17th APRIL 2006 | DECEMBER 31, 2007 |
44 |
RASGAS |
RFQ-D5648-09 ONSHORE PIPELINE INSTALLATION WORKS FOR RASGAS OFFSHORE EXPANSION PROJECT PHASE II . 2 x Dia 38” (WH-6/WH-8) x 5.4 km – 2 No. Parallel Pipelines |
06th DECEMBER 2005 | JANUARY 22, 2009 |
45 | QATARGAS | NPCC CONTRACT NO. 4059, EPC FOR QATARGAS II DEVELOPMENT PROJECT – OFFSHORE FACILITIES – ONSHORE PIPELINE AND CABLE LAYING WORKS
|
08th SEPTEMBER 2005 | 03rd AUGUST 2010 |
46 | QATAR PETROLEUM |
GTC 04/243/ED, EPIC Of COMMON UTILITIES AND FACILITIES FOR LIQUID PRODUCT BERTHS 1A & 1B TOPSIDES AT RAS LAFFAN EPIC contract with Medgulf responsible for Engineering, Procurement, Installation & Commissioning of Works.
|
27th FEBRUARY 2005 | 11th NOVEMBER 2010 |