NORTH FIELD SUSTAINABILITY PROJECT ( NFPS) Role : Onshore Construction (Subcontractor) Project Objective: CONSTRUCTION OF ONSHORE 1 x 38”, 2 x 32” INCH PIPELINE PROJECT IN RASLAFFAN- ONSHORE CONSTRUCTION WORKS Project Brief: Construction of Approximately 6 Kilometres 1 no. of 38” Carbon Steel ( CRA ) Pipelines + 1 x 32” Carbon Steel Pipeline from LTE to Qatargas South Plant including Onshore Trench Excavation Sand bedding under the Pipeline, Transportation, Stringing, lowering, fit up, welding assistance, installation of pipelines, Additional 1 x 32” Pipeline from LTE to Qatargas North Plant Construction of Beach Valve Pits , FOC cabling, installation of chemical inject skid.
START DATE : Jul 2021